Cable reuse is the core method to control construction workload during all-optical transformation. Each cable type needs separate evaluation. For incoming fiber, we check splice quality and optical attenuation; for Cat5e Ethernet cables, we run link tests and match service requirements; for POF, we verify physical integrity. Clear pass criteria, failure symptoms and reuse limits are defined for every category.
Reuse is not a blanket permission; each cable segment is assessed individually.
The AINOPOL IP-POL Boundary-Free Solution divides on-site work into retain, replace and add, and cable reuse falls into the "retain" category. Two points must be confirmed for every cable: reuse conditions and failure indicators. Cables with acceptable optical power, intact connectors and minor aging can be retained. Segments with excessive loss, fully occupied fiber cores or corroded RJ45 connectors will be marked for replacement or new deployment.
Judgment relies strictly on site survey rather than visual inspection. Engineers verify optical power budget, optical power difference among terminals on the same PON port, splitting ratio, port density and cable aging status link by link. Missing field data will lead to re-evaluation and scheme revision.
Each item clarifies applicable segment, pass criteria, failure symptoms and reuse boundaries.
表格
| Cable Type | Deployment Segment | Conditions for Reuse | Failure Indicators | Reuse Boundary |
|---|---|---|---|---|
| Incoming drop fiber | Hotel four-in-one service / FTTB access | Optical power within normal range, intact splices and routing, valid splitting ratio | Bent fiber, oxidized cold splices, out-of-spec optical loss | Only core and terminal devices are swapped; fiber and routing remain untouched, no recabling |
| Floor-to-room fiber | FTTB deployment | Intact fiber-to-room links, sufficient port capacity | Excessive attenuation, all fiber cores occupied | Replace MDU on-site; splices and routing unchanged |
| Cat5e / Cat6 Ethernet cable | Self-built triple-play networks, office areas in old buildings | Passes field test, no moisture or oxidation, supports original services | Corroded RJ45, locked at 100Mbps, intermittent disconnection, blocked conduits | Keep for original services or transitional use; faulty segments phased out per cutover plan |
| POF trunk & branch cable | Leased FTTR-B networking | Intact pre-laid trunk and drop cables | Damaged jacket, failure of either data or power delivery | Full cable reuse; only core and terminal hardware replaced, no decoration damage |
| Backbone optical cable | Core room to weak-current cabinets on floors | Functional fiber, available cable trays and conduits | Insufficient fiber cores, excessive attenuation | Keep backbone fiber; replace copper drops with fiber, no extra tray expansion or wall breaking |
| Legacy copper / telephone / CATV cable | Separated self-built triple networks | Still carrying legacy services | Aged and non-functional, high risk for live circuits | Gradually retired following cutover plan; reserved as rollback backup until acceptance |
Note: Standard optical fiber is used for backbone runs, while POF optoelectronic composite cable is only adopted for terminal drops. The whole link cannot use POF from start to finish.

All boundaries above apply to specific cable segments. The final reuse scope is subject to on-site survey and project design.
Do not remove old copper cables immediately. Keep them for rollback until acceptance, and complete compliance deployment in one renovation phase.
During phased cutover, legacy links stay online. Engineers can revert to the original circuit instantly once faults occur. Rollback procedures are documented, and as-built drawings clearly mark reused and newly deployed segments. Retaining legacy cables and devices through acceptance is a mandatory prerequisite for safe rollback.
Compliance capabilities are deployed together with network upgrade without extra downtime: real-name authentication with individual accounts and automatic expiry, local log storage for no less than 180 days with exportable complete fields, VLAN isolation between guest Wi-Fi and internal LAN, and one-click report export for inspection by room number or mobile number. These functions are provided locally by the Mengxiang Gateway, and logs never leave the local gateway. One optoelectronic AP in each room integrates internet, IPTV and voice services; local intercom remains available even when the uplink fails.
To sum up, every reusable cable needs independent inspection: incoming fiber, POF, backbone fiber and qualified Cat5e cables all have their own acceptance rules and failure limits. Legacy copper cables are reserved as backup rollback links before acceptance. The IP-POL Boundary-Free Solution records reuse rules in checklists and survey documents. All final arrangements depend on site survey and project plan.
Q: Can Cat5e cables still be used?
A: It can be retained if it passes on-site testing and runs original services stably. Segments with oxidation, moisture, speed downgrade or random disconnection will be phased out. The decision is based on optical/electrical test results and aging status, subject to site survey and project scheme.
Q: Should we remove old copper cables?
A: No rush. Legacy cables and devices are kept online until acceptance for rollback during phased cutover. As-built drawings label reused sections. Cables will be disposed after acceptance according to the plan.
Q: Will cable reuse affect project acceptance?
A: No. The reuse scope, link-by-link optical test records and as-built drawings are included in acceptance documents, with boundaries written into implementation files. Everything is subject to on-site survey and project design.